“The administration's infrastructure development remains sustained, strategic and on schedule.”
Ferdinand Marcos Jr. Claim dated 22 Jul 2024.
Vera Files rated thisNeeds context

What Vera Files found

The completion dates of at least six of the 185 Infrastructure Flagship Projects, including the Samal Island-Davao City Connector Bridge, the Metro Manila Subway Project and the Metro Rail Transit Line-7, have been adjusted due to delays involving mostly right of way issues.

Their words, from the summary they publish with the rating.

In short

Ferdinand Marcos Jr. made this claim around 22 July 2024. Vera Files (Philippines) looked into it and published its finding on 6 August 2024, 15 days later. Its rating was “Needs context”.

Ferdinand Marcos Jr. has 62 checked claims in this archive. Fact-checking organisations rated 17 of them false or fake, 43 misleading or mixed and 0 true.